Evergreen Expansion Update

 

evergreen independent living resized 5 5 16evergreen pac resized 5.5.16


In 2010 Evergreen initiated a Master Site Plan project with six phases of development. On August 30, 2016 the Evergreen Board of Directors unanimously approved to proceed with the final two phases.

It will include 41 new spacious independent apartments and  a new main entrance, additional parking, a new chapel and performing arts center, a game room and expanded library.

Construction will begin mid-September with the removal of the homes. We anticipate the entire project will be complete in the fall of 2017.

For continuous updates and more information about our plans, please come back to this page often.

View the New Apartment floor plans Here.
Expansion Project Frequently Asked Questions

April 14, 2017
  • Work continues in the Worship and Performing Arts Center. Starting Wednesday, April 19 crews will begin using a concrete saw to complete the removal of the exterior wall that will connect the space to our existing building They will also cut a hole through the floor of the existing building to lower level, this is expected to take 3 day and during this phase section of the Behnke Center will be blocked off.
  • Crews are framing out the new front office, game room, mail center, convenience store and public bathroom spaces behind the temporary wall.

  • Drywall work on the new offices behind the temporary wall in Manor North has begun.

Please note that the above work will create significant noise during working hours of 8:00am to 5:00pm.

  • The roofing crew will wrap up their work in the next 7-10 days. Once complete they will install the new doors and windows.

  • Plumbers and Electricians have begun working in the new apartments in the next week.

  • A reminder to please be cautious when entering underground parking as construction equipment is still moving about. As always if you need any help getting your car in the garage, please call Tom (920) 237-2147

(Please note all dates are subject to change)

 

 

March 24, 2017

· Next week crews will begin work to remove the exterior wall to connect the new Worship & Performing Arts Center to the existing building.

· Crews will continue framing out the new office spaces behind the temporary wall and installing the steel beams structure for the Worship & Performing Arts Center.

Please note that the above work will create significant noise during working hours of 8:00am to 5:00pm.

· The 3rd floor pre-assembled wood walls installation is complete and crews are working on framing the architectural cornices and preparing install the roofing foundation material.

· A reminder to please be cautious when entering underground parking as construction equipment is still moving about. As always if you need any help getting your car in the garage, please call Tom (920) 237-2147

· Regularly scheduled activities in the Chapel have relocated to their new locations. For a list of locations please see your calendars or the postings outside the former Chapel Space.

 

March 10, 2017

• Crews will begin work to extend the temporary wall around the Chapel from the former south entrance all the way around to the temporary wall on the northwest side of the Chapel near the Front Desk. This will allow crews to begin work to transform the space for its new purposes. Please note that the Way-finding TV, Foundation Giving Trees and the Coffee Station will be removed.

• Regularly scheduled activities in the Chapel will relocated to their new locations. For a list of locations please see your calendars or the postings outside the Chapel Space.

• Next week crews will begin framing out the new office spaces behind the temporary wall and installing the steel beams structure for the Worship & Performing Arts Center. Please note that this work will create significant noise during working hours of 8:00am to 5:00pm.

• Crews have begun installing the 3rd floor pre-assembled wood walls.

• Underground parking access restrictions have been lifted and residents may enter at any time. Please be cautious when entering as construction equipment is still moving about. As always if you need any help getting your car in the garage, please call Tom (920) 237-2147.

• Progress of the construction can be viewed from the Manor North Lounge windows.

(Please note all dates are subject to change)


February 24, 2017

• A temporary wall has been constructed down the Manor North hallway all the way to the south entrance of the Chapel, so crews can begin work on the new entrance and offices. The temporary walls will remain in Manor North, the Main entrance and corresponding community spaces until construction is complete in 2018.
• An additional temporary wall has been erected to close off the hallway on the north west side of the Chapel near the Front Desk.

• Activities regularly scheduled in the Chapel will relocate to the following locations:
Spiritual Services (Starting March 11th)
• Sunday 10 am - Catholic Communion service in the Behnke Center
• Sunday 3:30 pm - Vesper service with local area pastors in the Behnke Center every Sunday with Ecumenical Communion Service on the 1st Sunday of the month
• Tuesday 10:30 am - Episcopal Communion Service the first Tuesday of the month in the Behnke Center
• Wednesday 10 am - Catholic Mass on the 3rd Wednesday of the month and Catholic Communion service all other Wednesdays in the Behnke Center

Brain Training (Starting February 28th)
• Starting February 28th will move to the Resident Community Room

News Group (Starting March 3rd)
• 1st Friday of the Month – Manor South and All other Friday’s – The Trellis

Monthly Blood Pressure Clinic (Starting February 2nd)
• Will be held in the Ruth Rowland Room

• The crew is continuing to install the 2nd floor pre-assembled wood walls and upon completion will being the 3rd floor.
• Underground parking access restrictions have been lifted and residents may enter at any time. Please be cautious when entering as construction equipment is still moving about. As always if you need any help getting your car in the garage, please call Tom (920) 237-2147
• The concrete floor is expected to be poured in the basement of the new apartments next week.
• Progress of the construction can be viewed from the Manor North Lounge windows.

February 14, 2017
• Internal changes to Manor North and the Chapel area are expected to begin Monday, February 20th.
          o A temporary wall will be constructed down the Manor North hallway starting at MN 1022 and will run parallel to the wall all the way to the south entrance of the Chapel. Residents will be able to access the Chapel through the accordion doors through the end of the month. Regularly scheduled activities are in the process of being rescheduled.
          o A temporary wall will also be constructed to close off the hallway on the back side of the Chapel near the Front Desk.

• First floor framing has been completed and trusses for the 2nd floor have been installed. The 2nd floor pre-assembled wood walls are expected to arrive and be installed starting Monday, February 13th.

• Due to some changes in the construction schedule the front parking lot will remain closed to through traffic until further notice.

• Underground parking access restrictions have been lifted and residents may enter at any time. Please be cautious when entering as construction equipment is still moving about.
         o As always if you need any help getting your car in the garage, please call Tom (920) 237-2147

• The concrete floor is expected to be poured in the basement of the new apartments next week.

• Progress of the construction can be viewed from the Manor North Lounge windows.

(Please note all dates are subject to change)
To view video's and photos of the construction visit our Facebook Page!


February 7, 2017

First floor framing and second floor trusses being installed. Much progress being made on our new Courtyard Residence Apartments!

February 3, 2017

• The pre-assembled wood walls are being installed for the first floor frame work. First floor framing is expected to take another two weeks.

• Trusses for the 2nd floor are expected to arrive the week of February 13th.

• Access to underground parking restrictions have been lifted at this time.
             o As always if you need any help getting your car in the garage, please call Tom (920) 237-2147

• We expect to open few more parking stalls in the front parking lot and to reopen the parking lot exit so traffic flow is back to normal.

• The concrete floor is expected to be poured in the basement of the new apartments next week.

• Electrical and Gas utility services have been connected to the new portion of the building.

• The 1st stairwell structure is done and crews are working on the elevator shafts and second stairwell in the new building.

• The Library Drop box has moved to the ShareHaven driveway through the remainder of construction.

• Progress of the construction can be viewed from the Manor North Lounge windows.


January 17, 2017

  • Precast is all set on the new apartment expansion and worship and performance arts center foundation’s. The next step is to pour a concrete leveling compound on top of the precast.

    • Pouring this toping will begin Wednesday, January 18th with the hopes of finishing end of day on Thursday, January 19th. To ensure they are able to complete this in the next two days before the weather gets bad again crews plan to start working at 6:00am and could be working as late as 7:00pm.

  • The pre-assembled wood walls are expected to arrive on Monday, January 23rd.

  • A reminder that the parking lot exit is closed indefinitely throughout construction. Some parking stalls are blocked off to create a turnaround in the center of the existing parking lot.  Access to underground parking is restricted during the day, due to large equipment moving about, but will re-open at 5pm each day.

    • If you need any help getting your car in the garage, please call Tom (920) 237-2147

  • Crews continue to work on the structure that will be a stairwell in the new building.

  • The Library Drop box has moved to the ShareHaven driveway through the remainder of construction.

December 19, 2016

  • Precast (pre-made concrete columns, beams and floor slabs) are scheduled to start being set on Wednesday, December 21st. The Precast will be set by large cranes, so you will notice a lot more larger equipment coming in and moving about.
  • Crews will continue work on the worship & performing arts center’s foundation place forms and pouring the foundation.
  • A reminder that the parking lot exit will close indefinitely. Some parking stalls are blocked off to create a turnaround in the center of the existing parking lot. Access to underground parking is restricted during the day, due to large equipment moving about, but will re-open at 5pm each day. If you need any help getting your car in the garage, please call Tom (920) 237-2147
  • The Library Drop box has moved to the ShareHaven driveway through the remainder of construction.
  • Due to cold temperatures the work on the roof of the Manor Building has temporarily been put on hold until temperatures get above freezing.

(Please note that all dates are subject to change due to weather.) 

To view video's and photos of the construction visit our Facebook Page!

 

December 5, 2016

  • Crews are working on waterproofing the new apartment foundation and back-filling these areas.
  • Block work in the basement of the new apartments continues.
  • Crews will continue excavating for the worship & performing arts center’s foundation and pouring footings and the foundation.
  • A reminder that starting this week the parking lot exit will close indefinitely. Some parking stalls will be blocked off to create a turnaround in the center of the existing parking lot. Access to underground parking is restricted during the day, due to large equipment moving about, but will re-open at 5pm each day.
  • The Library Drop box has moved to the ShareHaven driveway through the remainder of construction.
  • A new roof is being installed on the Manor Building above Manor View and is expected to be complete the week of the December 20th.

(Please note that all dates are subject to change due to weather.) 

To view video's and photos of the construction visit our Facebook Page!



December 1, 2016

Parking & Transportation Update

As construction progress continues with the excavation of the Worship & Performing Arts Center access to existing parking in the parking lot, on Westfield Street, will be limited over the next few weeks. Alternate parking can be found on:

- North Westfield Street (South of the parking lot)

- North Eagle Street (Use the Garden Building entrance to access the building.

- Parking lots on North Eagle Street

Evergreen Transportation Pick Up Change

If you use Evergreen Transportation please note that pick up location has moved to the Garden Place Entrance on North Eagle Street. This will remain in effect until further notice.

November 19, 2016

This morning Saturday, November 19 a concrete wall that was under construction near Manor North collapsed and caused some damage to the existing manor building. Luckily, no one was injured during this incident. The construction company and other contractors are currently onsite working on the affected areas. More information will be provided as it becomes available. 

November 14, 2016

  • Work continues on the foundation of the new apartments. Two sections of wall have been poured and the crew is working on pouring the next section of footings and the basement walls.
  • A concrete block work is well under way for the stairwell and fire wall that will connect the existing Manor North building (west entrance) to the new structure is being built. Crews will also begin work on the interior walls of the underground parking structure out of concrete block.
  • The basement windows in the Behnke Center will be blocked in, starting Monday, November 14, in preparation for the grade change of the ground upon the completion of the chapel & performing arts center.
  • Crews are expected to begin excavating for the chapel & performing arts center’s foundation on Wednesday, November 16.
  • Starting the week of November 28th the parking lot exit will close indefinitely through the remainder of construction. Some parking stalls will be blocked off to create a turnaround in the center of the existing parking lot. Access to underground parking will remain open during this time.
  • The Library Drop box will be moving to the ShareHaven driveway through the remainder of construction.
  • Progress of the construction can be viewed from the Manor North Lounge windows.


November 8, 2016

Construction is progressing and we have a few updates to share with you:

  • Work continues on the foundation of the new apartments. One section of wall has been poured and the crew is working on pouring the next section of footings and the basement walls.
  • The basement windows on the west side of Manor North have been blocked in, with concrete blocks, in preparation for the grade change of the ground upon the completion of the chapel & performing arts center.
  • Crews are expected to begin excavating for the chapel & performing arts center’s foundation in about two weeks.
  • Work on the new front parking lot is beginning with the installation of storm sewer and utilities. Once the utilities are in this area will be used as a staging area for building materials for the new apartments.

(Please note that all dates are subject to change due to weather.) 

To view video's and photos of the construction visit our Facebook Page!

 

October 31, 2016

Work on the digging for the foundation continues and some of the footings for the basement of the new structure have been poured. Forms for the basement walls were delivered and crews are expected to start work on those next week. The foundation portion of the project is expected to take about 4 – 5 weeks.
img 1021 web(Please note all dates are subject to change due to weather)



October 14, 2016

Digging for the foundation of the new apartments has begun and the excavation crews are prepping the ground for the concrete crews to arrive next week, where they will begin work on the footings and foundation for the basement of the new structure. This portion of the project is expected to take about 4 – 5 weeks. (Please note that all dates are subject to change due to weather.) 
Check out the excavation crew in action and for more exciting video's and photos visit our Facebook Page!




October 4, 2016

A historic day here at Evergreen! As a chapter comes to an end a very exciting one is beginning, and it is fitting that the first Evergreen Home to be built is the first one to come down, in the name of progress, to make way for our new apartments. For more exciting video's and photos visit our Facebook Page!

 

September 22, 2016

On August 31, we announced to you that the Evergreen Board of Directors unanimously approved to proceed with the final two phases of our Master Plan. Since then we have some exciting updates to share with you:

• Exterior updates on Manor South are wrapping up and exterior updates on Manor North are beginning this week. Crews will be working, as they are able, to complete this project in October.
• The Homes on the north side of campus will start to be taken down the week of 10/3.
• Digging for the foundation of the expansion will begin the week of 10/10. Fencing will surround the job site and the area from the existing parking lot to the sidewalk will be cleared to make space for equipment and materials.
• Once the expansion is excavated, the crew will move just north of the main entrance and start digging for the foundation and future Chapel and Performing Arts Center.

(All dates subject to change due to weather)

We will continue to post updates on a regular basis.